Concrete calculator icon for working out cubic yards, cubic metres and bags of concrete mix for a slab, footing, post hole or steps

Concrete Calculator

Pick the job, and get cubic yards, cubic metres and every common bag size with waste already added

Measured in
Slab, patio or driveway length × width × thickness
ft
ft
in
What to order, waste included Bag counts are rounded up to whole bags. Weights show what you will carry and mix.
Cubic yards…
Cubic metres…
Cubic feet…
80 lb bags…
60 lb bags…
40 lb bags…
25 kg bags…
20 kg bags…
Wet weight…
Best way to buy…
Working…

What one bag of concrete mix makes

Yields are for fresh mix as the maker states it. The tool rounds every count up to a whole bag, and uses the lower 20 kg figure so a small job does not run one bag short.

BagYield per bagPer cubic yardPer cubic metreWhere the figure comes from
80 lb (36.2 kg)0.60 ft³, 17 L4559US maker data sheets
60 lb (27.2 kg)0.45 ft³, 12.7 L6079US maker data sheet
40 lb (18.1 kg)0.30 ft³, 8.5 L90118US maker data sheet
25 kgabout 0.012 m³, 12 L6484UK trade figure
20 kg0.009 to 0.010 m³85110AU and UK makers

A yard of 80 lb bags is 3,600 lb of dry mix to lift, tip and stir, which is why ready mix wins long before the price does. Yields assume the water the maker recommends, about 6 pints for an 80 lb bag.

Ordering a pour, in order

The sequence that keeps a truck from leaving you a wheelbarrow short.

  1. 1Measure the forms, not the plan. A slab dug 1/8 inch deeper than drawn is already 3% short on a 4 inch pour.
  2. 2Pick the job chip and enter lengths in feet or metres, thickness and diameters in inches or centimetres.
  3. 3Keep 10% waste for slabs and walls. Go to 15% for hand dug holes and footings, where the ground is the form.
  4. 4Under half a yard, buy bags. From a yard up, call a ready mix plant and ask for their minimum and short load fee.
  5. 5Near the end of a big pour, re-measure what is left and phone the plant before the last truck is batched.
Guide

How much concrete to order, job by job

The one conversion that matters, the six jobs people actually pour, what a bag really makes, and where bags stop making sense.

A concrete calculator has one job: turn the size of a pour into an order you can place, whether that is a number of bags at the store or a number of cubic yards on the phone to a ready mix plant. This one starts from the job rather than the shape, so a slab, a strip footing, a poured wall, a round column, a row of post holes and a flight of steps each ask for the measurements a builder would actually take. The answer comes back in cubic yards and cubic metres, with 80, 60 and 40 lb bags and 25 and 20 kg bags counted side by side and the waste allowance already included.

If what you need is the volume of a shape that is not a pour, such as a tank, a cone of gravel or a room, the volume calculator covers generic solids and the area calculator handles the footprint. This page stays with concrete.

The only conversion you have to remember

Concrete in the US is sold by the cubic yard, and a cubic yard is 3 ft by 3 ft by 3 ft, which is 27 cubic feet. So every job comes down to the same two steps: find the volume in cubic feet, then divide by 27. Thickness is the trap, because it is measured in inches and has to become feet first. A 4 inch slab is 4 / 12 = 0.333 ft thick, and that is where the old trade shortcut comes from: at 4 inches, one cubic yard covers 81 square feet, so square footage divided by 81 gives cubic yards. At 6 inches the same yard covers only 54 square feet.

In metric countries the unit is the cubic metre, and the arithmetic is kinder because thickness in centimetres divides by 100. One cubic yard is exactly 0.764555 cubic metres, so a metric order is about three quarters of the yard figure. The tool shows both so a US spec and a UK or Australian supplier can be compared without a second calculation.

Slabs, patios and driveways

A slab is length times width times thickness. Concrete Network puts residential patios, walks and driveways at 4 inches and garage floors and heavy duty driveways at 5 to 6 inches; CalculatorSoup's guide adds 6 inches for a hot tub pad. The thickness choice moves the order more than anything else on a slab: a 10 by 10 ft slab is 1.24 cubic yards at 4 inches and 1.85 at 6, which is 56 against 84 bags of 80 lb mix before any waste. Worked through the tool, a 20 by 10 ft patio at 4 inches is 66.7 cubic feet; with 10% waste that is 73.3 cubic feet, 2.72 cubic yards or 2.08 cubic metres, and 123 bags of 80 lb mix if you insisted on mixing it by hand.

Strip footings and poured walls

A strip footing is a long, shallow slab under a wall, so enter the total run length in feet and the width and depth in inches. Under the International Residential Code, section R403.1.1, a concrete footing is never less than 12 inches wide or 6 inches thick, and Table R403.1 widens it for more stories or weaker soil; on 2,000 psf soil a two story light frame house needs 15 inches. Check your local code before you dig, because your building department sets the real number. A poured wall is the same box turned on its side: length times height times thickness, with the height in feet and the thickness in inches.

Round columns and piers

A column or pier poured in a cardboard tube form is a cylinder, so the volume is π times the radius squared times the height. Enter the tube's diameter in inches and the height in feet, and set the count to the number of piers. The count matters more than it looks: four 12 inch piers 8 feet tall are just over 25 cubic feet, which passes a full cubic yard once 10% waste is added.

Post holes, with the post taken out

This is where almost every concrete calculator overestimates. A post hole is not a solid cylinder of concrete, because the post stands in it. Quikrete's data sheet sizes the hole at about three times the post width and one third of the post's height deep, with 6 inches of concrete placed under the post first. The tool follows that: it works out the hole, then subtracts the post from the level of that bottom layer up to the surface. Enter the post's actual size, not its name. A nominal 4x4 is 3 1/2 by 3 1/2 inches and a 6x6 is 5 1/2 inches. For a 4x4 in a 10.5 inch hole 32 inches deep, the concrete is 1.42 cubic feet rather than 1.60, so the post fills about 11% of the hole, and a calculator that ignores it orders 13% too much. Over a fence line of twenty posts that is several bags you do not have to buy.

Steps

Solid steps poured against the ground are a staircase of boxes. The bottom step is one rise tall, the next is two rises tall, and so on, so the volume is width times tread times rise times n(n + 1) / 2 for n steps, plus any landing at the top. The code limits under IRC R311.7.5 are a riser of no more than 7 3/4 inches and a tread of at least 10 inches, with no more than 3/8 inch variation between steps in one flight. Four steps at a 7 inch rise and 11 inch tread, 4 feet wide, come to about 21.4 cubic feet. If you fill the core of a large set of steps with compacted gravel, measure the concrete as the shell you are actually pouring.

Why the waste allowance is 10 percent, and when it should be more

Nearly every calculator tells you to add 10 percent. The reason is in the National Ready Mixed Concrete Association's note on yield: forms bulge, subgrade is never perfectly flat, and thickness errors are proportionally huge. A slab dug just 1/8 inch deeper than planned on a 4 inch pour is 3 percent short, which on a 32 yard order is a whole yard. Hardened concrete in place can also measure about 2 percent less than the fresh volume that was delivered. NRMCA's advice is to order at least 4 to 10 percent over the estimate, and more for irregular work such as footings, walls and fill around pipes. Cemex suggests 10 to 15 percent. The tool defaults to 10 and offers 15 for dug holes and footings, where the ground itself is the form.

What a bag actually makes

Bag counts only make sense against the maker's stated yield. Quikrete's Concrete Mix data sheet gives 0.30 cubic feet for a 40 lb bag, 0.45 for a 60 lb bag and 0.60 for an 80 lb bag, and Sakrete's data sheet gives the same 0.60 for its 80 lb bag. That is 90, 60 and 45 bags to the cubic yard. Metric bags are less consistent. Cockburn Cement in Western Australia states 0.009 cubic metres, or 110 bags per cubic metre, for its 20 kg concrete pack, while Blue Circle's 20 kg ready to use concrete in the UK is sold as making around 0.01 cubic metres. The tool counts 20 kg bags at the lower yield so you do not run one bag short, and counts 25 kg bags at about 0.012 cubic metres, the figure UK suppliers quote. Always check your bag's printed yield before a large order, because it changes with the brand.

The number that surprises people is the weight. A cubic yard of 80 lb bags is 45 bags and 3,600 lb of dry mix to lift, tip and stir. Quikrete also asks for about 6 pints of water per 80 lb bag and at least 1 cubic foot of mixer drum for every 80 lb bag mixed at once. That is why the tile row shows the weight to lift under each bag count.

Bags or ready mix

Bags win on small jobs: fence posts, repairs, a pad for a shed. Ready mix wins on anything big: Concrete Network suggests bags for walkways, small patios and footings and ready mix for driveways and larger patios. The switch point is a matter of volume and effort. Cemex will not deliver less than one cubic yard, and UK guidance puts the point where ready mix becomes cheaper somewhere between 0.5 and 1.0 cubic metres. The tool reads the order and says so: under half a yard it says bags, from half a yard to a yard it says price both, and from a yard up it says ready mix. A full truck carries about 8 yards on average and up to 10, so anything well under that attracts a short load fee.

What concrete costs in 2026

Prices vary by region and by how far the plant is from you, so treat these as a sense check rather than a quote. LawnStarter's guide, updated in December 2025, puts ready mix at $120 to $150 per cubic yard, with a short load charge of about $43 per yard below a truckload and delivery of $18 to $20 per yard. SlabCalc's 2026 guide, updated in September 2026, puts delivered ready mix at $125 to $175 per cubic yard with a $50 to $100 short load fee. In the UK, 2026 guidance puts delivered ready mix at £110 to £185 per cubic metre before VAT, with 25 kg bags at roughly £5.50 to £9 each. Ask your plant for its minimum load and its short load fee before you compare against bags, because on a one yard pour the fee can be a large part of the bill.

How much it weighs

Normal ready mix weighs about 150 lb per cubic foot, so a cubic yard is roughly 4,050 lb; Concrete Network and Cemex round that to about 4,000 lb, or two tons. In metric terms that is about 2,300 to 2,400 kg per cubic metre. Bagged mix is a little lighter; Quikrete lists its Concrete Mix at about 140 lb per cubic foot. The weight tile uses 150 lb per cubic foot, which is the figure to plan a trailer, a wheelbarrow route or an elevated form around.

After the pour

Quikrete asks for moist curing for 5 days in weather of 70 °F or warmer and 7 days between 50 and 70 °F, and for protection from freezing for the first 48 hours. CalculatorSoup's rule of thumb is foot traffic after 24 to 48 hours, cars after about 7 days, and near full strength at about 28 days, which matches Quikrete's 4,000 psi rating at 28 days against 2,500 psi at 7. Cut control joints about 1 inch deep every 6 to 8 feet on a slab so the cracks go where you choose.

FAQ

Frequently Asked Questions

How many bags of concrete does a 10 by 10 slab take?

At 4 inches thick a 10 by 10 ft slab is 33.3 cubic feet, or 1.24 cubic yards. That is 56 bags of 80 lb mix with nothing spare. Add the usual 10% for waste and it becomes 62 bags of 80 lb mix, or 82 bags of 60 lb mix. At 6 inches the same slab is 1.85 cubic yards, which is 84 bags of 80 lb before waste, and at that size ready mix is usually the better buy.

Should I subtract the post when working out concrete for a post hole?

Yes. The post fills part of the hole, and most calculators ignore it. For a 4x4 post, which is really 3 1/2 inches square, set in a 10.5 inch hole 32 inches deep on 6 inches of concrete, the hole holds 1.60 cubic feet but only 1.42 cubic feet of it is concrete. The Post holes chip does this subtraction for you. Enter the post's actual size, not the nominal one.

How many 20 kg bags of concrete make one cubic metre?

Between about 100 and 110, depending on the brand. Cockburn Cement states 0.009 cubic metres per 20 kg bag, which is 110 bags per cubic metre, while Blue Circle's 20 kg ready to use concrete is sold as making around 0.01 cubic metres, which is 100. This calculator uses 110 so you are not left one bag short, then adds your waste allowance on top.

Is a 25 kg bag of concrete roughly the same as a 60 lb bag?

Close, but a little smaller. 25 kg is about 55 lb, and a 25 kg bag makes about 0.012 cubic metres, which is 0.42 cubic feet. A 60 lb bag makes 0.45 cubic feet. So you need about 64 bags of 25 kg for a cubic yard against 60 bags of 60 lb. The tile row shows both counts at once, so you can buy whichever your store stocks.

At what size does ready mix work out better than bagged concrete?

Around half a yard to one yard. Cemex will not deliver less than one cubic yard, and UK guidance puts the point where ready mix becomes cheaper somewhere between 0.5 and 1.0 cubic metres. Effort matters too: one cubic yard is 45 bags of 80 lb mix, or 3,600 lb to lift and mix. The Best way to buy tile applies this for you.

Why did my pour come up short when the numbers looked right?

Usually because the forms held more than the plan said. The National Ready Mixed Concrete Association points out that a slab just 1/8 inch thicker than planned on a 4 inch pour needs 3% more concrete. Bulging forms, uneven subgrade and spillage add to that, and hardened concrete can measure about 2% less than the fresh volume delivered. NRMCA advises ordering 4 to 10% over the estimate, and more for footings and irregular work.

How thick should a concrete garage floor or driveway be?

Concrete Network gives 4 inches for patios, walks and ordinary residential driveways, and 5 to 6 inches for garage floors and driveways that carry heavy vehicles. Going from 4 to 6 inches adds half again to the concrete, so settle the thickness before you price the job. Local code or an engineer's drawing overrides any rule of thumb.

How wide and deep does a house footing have to be?

Under the International Residential Code, section R403.1.1, a concrete footing is at least 12 inches wide and 6 inches thick, and Table R403.1 makes it wider for taller houses or weaker soil. On 2,000 psf soil a two story light frame house needs a 15 inch footing, for example. These are minimums, and your building department has the final say on both size and depth.

What step height and tread depth should I use for concrete steps?

The International Residential Code, section R311.7.5, allows a riser of no more than 7 3/4 inches and asks for a tread of at least 10 inches, with no more than 3/8 inch difference between the tallest and shortest step in a flight. Divide the total height by 7 3/4 and round up to get the number of steps, then enter that number with the actual rise and tread in the Steps chip.

What does a cubic yard of ready mix concrete cost in 2026?

In the US, recent guides put it at roughly $120 to $175 a cubic yard delivered, depending on region and distance from the plant. LawnStarter's December 2025 update gives $120 to $150 plus about $43 a yard for a short load, and SlabCalc's September 2026 guide gives $125 to $175 with a $50 to $100 short load fee. In the UK, 2026 guidance puts it at £110 to £185 a cubic metre before VAT. Get a quote from your local plant before you commit.